Home
Home Home
       
Im
Back to Anglo Platinum  | Downloads  | Glossary  | Contact  
Home
Im
       Home
   
     Profile & mission
   
     Key features
   
     Chairman‘s statement
   
     The board & executive
   
     CEOs‘ review
   
     Finance review
   
  +   Market review
   
       Operations review
Safety
Human resources
Black economic empowerment (BEE) transformation
Mining
Process
   
     Ore reserves & mineral resources review
   
     Projects review
   
  +   Company statistics
   
  +   Financial statements
   
  +   Directorate &
management
   
  +   Shareholders‘
information
   
Operations review  |  Mining
In this section
Rustenburg
Amandelbult
Union Section
Potgietersrust Platinums Limited (PPRust)
Lebowa Platinum Mines
Twickenham
Bafokeng-Rasimone Platinum Mine (BRPM)
Modikwa Platinum Mine
Kroondal Platinum Mine
Marikana Platinum Mine
Mototolo Platinum Mine
 
   
 
Im
 
   
Rustenburg Section (managed – 100% owned) (continued)
Projects
Rustenburg Section
Project teams at Rustenburg Section had 15 lost-time injuries on both green- and brownfields projects, resulting in a LTIFR of 0.85. To address safety, major emphasis has been placed on leadership, safe planning and the Anglo Safety Way to achieve zero harm. There are areas of excellence, with Waterval Phase 2 progressing for three years and eight months without a lost-time injury.
print   print page
email   email page
download   PDF 2.7MB
   
Rustenburg UG2 Phase 2 project
This project was initially approved in 2002. Changing global economic conditions required a scope change, which was approved in February 2006 with a reduction in output from 400,000 to 275,000 tonnes per month.

The Townlands and Frank sections of the project have been completed and successfully ramped up to steadystate production levels. The Boschfontein West capital footprint has been completed with only construction of the surface ventilation remaining, scheduled for completion in early 2008.

To enable continued mining at Boschfontein, pre-feasibility study work on the 10 to 14 level ore replacement project has been completed. The pre-feasibility report is being evaluated to determine the viability of this project.
 
   
   
 
Paardekraal Merensky Replacement project
The Paardekraal No 2 shaft project is designed to restore Merensky reef output at Paardekraal, in line with the overall Rustenburg mining strategy. The aim is to mine Merensky reef as the base operating horizon, due to its higher unit value, to ensure sustained profitability. The UG2 horizon would be used to fill spare shaft-hoisting capacity, but not at the expense of Merensky production.

The medium-term Rustenburg mining profile is predicated on a series of phased decline extension projects to existing shafts. Between 2014 and 2020, the production profile will be maintained by using either two or three intermediate vertical shafts. The Paardekraal 2 (PK2) shaft is the first of these vertical shafts.

The first blast for construction of the ventilation shaft took place in September 2006 while construction of the man-and-materials shaft began in September 2007. Steady-state production from this shaft will reach 120,000 platinum ounces per annum in 2015. 
 
Other Rustenburg section replacement projects 
Replacing ore reserves on both the Merensky and UG2 reef horizons has necessitated the deepening of existing mine infrastructure at Frank, Paardekraal, Townlands and Turffontein on the Merensky horizon, and Waterval on the UG2 horizon.

A pre-feasibility study was conducted for a deep Merensky shaft north of the existing Frank and Turffontein shafts, to exploit deeper Merensky reserves and sustain Merensky production at Rustenburg Section. The study unfortunately concluded that a deep-shaft approach, addressing the entire orebody, is not presently viable based on the prevailing long-term outlook. A concept study has thus been initiated to incorporate further options.

The Merensky ore reserve replacement projects for Frank and Turffontein shafts were approved in 2005 and are nearing completion. The Turffontein project is being handed over to mining operations while the final handover of the Frank project has started and will be completed in the second quarter of 2008. Pre-feasibility study work on the Frank and Turffontein UG2 projects has been concluded and a feasibility study is planned to take place in 2008.

The Waterval Phase 3 project was approved in December 2006 and development is progressing satisfactorily. This project will contribute 52,000 ounces of platinum production at steady-state in 2009. The Waterval Phase 4 and 5 replacement studies are under way.

The Townlands ore replacement project aims to replace diminishing Merensky Reef output at that shaft by extending the existing decline shaft. Final approval was granted in February 2007 and the project is now in execution phase and progressing well towards achieving its steady-state output of 70,000 platinum ounces per annum by 2014.
 
image image
Tom van der Nest Tom van den Berg
   
 
 
  Page up  
  Page  1  2  3  4  5  6  7  8  9  10  11  12  13  14  15  16  17  18  19  20    

Previous page  |  Operations review 8/20
 
   
  Home
  Disclaimer  
Home  
 
Valid HTML 4.01 Transitional